The information contained in the project agreement and schedules about expected service delivery specifications is reasonable in terms of the required services to be delivered. The project agreement also includes a comprehensive performance monitoring and reporting regime.
Partnerships Victoria guidelines were not fully complied with in terms of the timing of development and finalisation of the CAM, with the CAM remaining incomplete at the time of this audit report.