We considered 25 PPP projects in NSW. Of these, 14 projects were initiated using the current NSW PPP policy and 7 of these have been completed. Of these, the standard agreement was simply a finance transaction and there is incomplete data on 1 project. To supplement these results a full data has been obtained on 2 other privately financed projects completed since 2000.
Partial data is also available on 4 of the currently ongoing projects.
Comparable Traditional projects were sought for these 13 PPP projects.
▼ Table C.2 New South Wales: PPP projects
_________________________________________
Source: Study results
Project name | Year 2000+ | Completed | Comment |
Alternative Waste Technology Facility | Yes | Yes | Full data |
Cross City Tunnel | Yes | Yes | Full data |
Lane Cove Tunnel | Yes | Yes | Full data |
New School Project #1 | Yes | Yes | Full data |
Newcastle Community Health Centre | Yes | Yes | Insufficient data |
Sydney Airport Rail - stations agreement | Yes | Yes | renegotiated |
West Sydney Orbit (Westlink M7) | Yes | Yes | Full data |
Bonnyrigg Living Communities Project (Social Housing) | Yes | Ongoing | Partial data |
Chatswood Transport Interchange | Yes | Ongoing | Insufficient data |
Long Bay Forensic And Prison Hospitals Project | Yes | Ongoing | Partial data |
Mater Hospital, Newcastle | Yes | Ongoing | Partial data |
New School Project #2 | Yes | Ongoing | Insufficient data |
Police Property Portfolio | Yes | Ongoing | Not a major procurement style |
RailCorp Rolling Stock | Yes | Ongoing | Partial data |
Broadwater Co-generation Plant II | No | Yes | Full data |
Parramatta Transport Interchange | No | Yes | Full data |
Eastern Distributor Toll Road | No |
|
|
Hawkesbury Hospital | No |
|
|
M2 Toll Road | No |
|
|
M4 Toll Road | No |
|
|