APPENDIX INFORMATIONAL OUTLINE OF THE FRAMEWORK POLICY

1 In the first step, the estimated capital cost of the project can have a margin of error of 20 to 100%

2 In the second step, estimated capital cost of the project can have a margin of error of 15 to 30%

3 In the third step, estimated capital cost of the project can have a margin of error of 0 to 5%.

* For a project possibly involving an architecture competition, the Conseil du trésor is the body that authorizes the drawing up of the initial business case.

APPLICATION PARAMETERS FOR THEFRAMEWORK POLICY FOR THE GOVERNANCE OF MAJOR PUBLIC INFRASTRUCTURE PROJECTS

The following is a translation of the official order in council 148-2010 signed on March 10, 2010, by Gérard Bibeau, clerk of the Conseil exécutif.