In the past five years, all Australian jurisdictions have issued policy documents governing the identification, establishment and operation of PPP arrangements. Victoria was the first to issue its guidelines under its Partnerships Victoria initiative. Soon after, in November 2001, New South Wales issued its Working with Government: Guidelines for Privately Financed Projects. Other states and the Commonwealth followed. All the guidance material had its origins in principles developed by the Heads of Treasuries working party.
The Committee's review of these documents highlighted that the governing principles or framework adopted by the different jurisdictions are broadly based on Victoria's PPP policy and guidelines. There are material variations on matters such as fair value compensation on termination, change in law and change of control provisions, they contain various technical and terminology differences, and they also follow slightly different processes for the development of a PPP project.
The Committee was advised that because of criticisms from industry that the PPP policy needs to be implemented more consistently to reduce bid costs, some limited progress has been made in achieving consistent principles and practices across jurisdictions. The National Council for PPPs, a forum for coordination between federal and state Ministers and officials, was set up in 2004 as part of the move towards having a more consistent approach to PPPs across all Australian jurisdictions.
The major differences in policies and practices are:
• core and non-core services - New South Wales, Victoria, Queensland, Western Australia, the Australian Capital Territory and the Northern Territory draw a distinction between core and non-core services, and expressly preclude private involvement in the provision of core services;
• value for money test - the framework in Queensland does not apply without special Cabinet committee exemption if the capital value of a project is $30 million or less or its net present value does not exceed $50 million. In Victoria, New South Wales, Northern Territory, and the Australian Capital Territory there is an explicit presumption that the project will generally not satisfy the value for money test unless it has a total contract value (in net present value terms) of more than $10 million (Victoria) or $20 million (New South Wales, Australian Capital Territory, Northern Territory) or can be bundled together with other similar projects to overcome that threshold. At the Commonwealth level, the $20 million and $50 million thresholds are only relevant for determining the level of approval required;
• long term -the duration of the project must not be less than 5 years for the Commonwealth; 25 years or more for New South Wales, the Australian Capital Territory and South Australia; and up to 30 years for Victoria.
• public sector comparator (PSC) - the New South Wales policy requires it be used for all projects, while the South Australian guidelines state that it is not necessary where the project is financially free-standing (consumer funding rather than government funding). The other jurisdictions follow Victoria's lead, which requires the construction and use of a PSC except in the rare situations where the Department of Treasury and Finance agrees that a PSC is not required. In that case, an appropriate benchmark still needs to be constructed to demonstrate value for money.
• release of the PSC - one way the policies diverge is in the matter of the PSC's release to the public and, more significantly, to bidders. The Commonwealth and SA policies have no general rule on release, and in those jurisdictions that do, approaches range from complete confidentiality to a general policy of release. The PSC is to remain confidential in Western Australia until the contract is executed, while Victoria, Tasmania and the Australian Capital Territory have a general rule against disclosure of the total PSC value.
The Committee observed that full adoption of the PPP model varies considerably across jurisdictions. Victoria and New South Wales are at the forefront; Queensland, South Australia, Western Australia and the Northern Territory have each completed one PPP. The Federal Government and the other Australian jurisdictions all have PPP policies in place but as yet have not completed a project. Exhibits 4.2 and 4.3 show the number and type of PPP projects either undertaken or in the pipeline.
Exhibit 4.2:
Completed or signed public private partnership
projects in Australia at July 2006
| Project | Cost ($ million) | |
| Commonwealth of Australia | Defence Headquarters Joint Operation Command Facility | 30099 |
| Northern Territory | Darwin City Waterfront Redevelopment/ Darwin Convention and Exhibition Centre | 1,100100 |
| New South Wales | New schools project #1 | 137101 |
| Cross City Tunnel | 680102 | |
| Western Sydney Orbital | 2,230103 | |
| Alternative waste technology facility | 75104 | |
| Lane Cove Tunnel | 1,100105 | |
| Parramatta Transport Interchange | 100106 | |
| Sunshine Electricity Company Co-generation Plants | 215107 | |
| Chatswood Transport Interchange | 360108 | |
| Western Australia | CBD courts complex | 195109 |
| Queensland | Southbank Education and Training Institute | 550110 |
| South Australia | Regional police stations & courts administration | 45111 |
| Tasmania | Risdon Prison redevelopment | 90112 |
| Victoria 113 | County Court | 195 |
| Docklands film and television studios | 40 | |
| Campaspe Water reclamation scheme (formerly Echuca Rochester Wastewater treatment plant) | 40 | |
| Victorian correctional facilities | 275 | |
| Emergency Alerting System | 100 | |
| Royal Women's Hospital redevelopment | 364.4114 | |
| Wodonga Wastewater Treatment upgrade | 32 | |
| Casey Community Hospital | 120 | |
| Southern Cross Station (formerly Spencer Street Station) | 309115 | |
| Mobile Data Network | 140 | |
| Metropolitan Mobile Radio | 120 | |
| EastLink | 2,500 | |
| Royal Melbourne Showgrounds redevelopment | 108 | |
| Melbourne Convention Centre development | 367116 | |
| Ballarat North water reclamation (Central Highlands) | less than 50 |
Exhibit 4.3:
PPP projects in the market in Australia at July 2006117
| Project | Estimated timing |
| Commonwealth Government of Australia | |
| Single Living and Environment Accommodation Precinct | EOI close - November 2005 Issued RFP (Part 1) - December 2005 |
| Mulwala Munitions Factory Redevelopment | RFT close - March 2005 Outcome expected in 2006 |
| New South Wales state government | |
| Bonnyrigg Living Communities Project (Social Housing) | EOI close - 30 March 2005 RDP issue - September 2005 RDP close - February 2006 |
| Forensic Hospital | RDP close - December 2004 Contractual close - second half 2005 |
| Mater Hospital, Newcastle | RDP close - December 2004 Contractual close - second half 2005 |
| Newcastle Port Multi-Purpose container terminal | EOI close - February 2003 RDP close - August 2005 Contractual close - early 2006 |
| Newcastle Community Health Centre | RDP close - 19 November 2004 Financial close - second half 2005 |
| RailCorp Rolling Stock | EOI close - 13 October 2004 RDP close - October 2005 Contractual close - mid 2006 |
| New Schools (second batch) | EOI close - May 2005 RDP close - September 2005 Financial close - early 2006 |
| Queensland state government | |
| Townsville Industrial Recycling | NM Rothschilds & Sons (Australia) announced as preferred partner for PPP in June 2005. Subject to market confirmation, Rothschilds will build, own and operate the recycling project. |
| North South Bypass Tunnel | Two short listed consortia have been invited to submit detailed tenders by December 2005. EIS approved by Queensland's Coordinator General. |
| Townsville Ocean Terminal | Preferred developer announced - September 2005 Contract Finalisation - December 2005 |
| Gold Coast Marine Development Project | EOI release - October 2005 EIS commenced - October 2005 |
| Victorian state government | |
| Barwon Water - Biosolids Management | EOI Close - 5 June 2005 Release RFT: Oct 2005 Contractual Close - May 2006 Facility completed - November 2007 |
| Royal Children's Hospital | Three short listed consortia have been invited to submit a full costed proposal for the hospital |
Exhibit 4.4:
Potential PPP projects at 10 July 2006118
| Projects | Possible release (to the market) |
| New South Wales state government | |
| Health related projects | |
| Water supply projects | |
| Queensland state government | |
| New Queensland Drivers License | + |
| Airport Link (North South Bypass Tunnel Stage 2) | + |
| Very High Speed Broadband (Project Visa) | + |
| Lockyer Water Reliability | |
| Gold Coast Public Transport | |
| Victorian state government | |
| Melbourne Wholesale Market Relocation | + |
| Housing Sector | % |
| Supreme Court Redevelopment | |
| Hospital Sector | |
| Research Facilities | |
| Water Sector | |
| Aged Care | |
| Western Australian state government | |
| Office Accommodation | + |
| Health Infrastructure | |
| Public Housing | |
The Committee's research confirmed that there are no general laws in any Australian jurisdictions governing PPP procurement.
__________________________________________________________________________________________________
99 The current total cost estimate for the HQJOC Project is approximately $300 million. The cost includes the buildings and infrastructure; the command, control, communications and information systems; land acquisition; workplace relocation costs, and design, professional fees and construction contingency; but excludes goods and services tax. Source: www.defence.gov.au/kid/hqjoc/pages/faq.htm, accessed 24 July 2006
100 www.waterfront.nt.gov.au/waterfront/about/index.html, accessed 24 July 2006
101 NSW Auditor-General's 2006 The New Schools Privately Funded Project, p 10
102 NSW Joint Select Committee on the Cross City Tunnel, p.22 - First Report February 2006
103 Source: www.mallesons.com/expertise/project_finance/5501627W-03.htm, accessed 24 July 2006
104 www.globalrenewables.com.au/en/operations/eastern-creek-ur3r-facility/, accessed 24 July 2006
105 Mr Carl Scully, MP, NSW Minister for Roads, media release, 9 December, 2003
106 www.parracity.nsw.gov.au/news/20020531_367.html, accessed 24 July 2006
107 NSW Budget Statement 2005-06, p.9
108 Has an estimated value on completion in excess of $360 million. http://cti.cri.com.au/, accessed 24 July 2006
109 www.wlg.com.au/about-the-project.html, accessed 24 July 2006
110 19 April 2005 Queensland Premier's Office, Included in this amount are construction costs of approximately $230 million
111 www.plenarygroup.com.au/content/newscentre/32, accessed 24 July 2006
112 www.smh.comau/news/National/Risdon-Prisons-infamous-past/2005/05/09/1115584891860.html, accessed 24 July 2006
113 Partnerships Victoria, website, www.partnerships.vic.gov.au
114 Partnerships Victoria, website, www.partnerships.vic.gov.au , $364.4 million tenders vic website $250 million
115 Partnerships Victoria, website, www.partnerships.vic.gov.au , $309 million; tenders vic website $341 million
116 Partnerships Victoria, website, www.partnerships.vic.gov.au , $367 million; tenders vic website $370 million
117 National Public Private Partnerships Forum: Projects in the Market, at July 2006 www.pppforum.gov.au