2.1.1  Set up the project team and governance structure

The complexity and scale of most PPP projects will usually justify a team-based management approach to ensure that all the required skills are effectively applied.

A common way of implementing effective project governance for PPP project development is by a system of boards or committees. Different systems can be considered, but they normally include:  Guidance 19

  a project board or "steering committee", comprising the main public sector stakeholders and led by a senior officer within the Authority who is responsible for delivering the project; and

  a project management team, responsible for managing the PPP project (including managing advisers) and reporting to the steering committee. Appointing a project director is of particular importance During the intense procurement phase, this will be a full-time job. The skill set should include familiarity with private business as well as an understanding of how government administration works