PPPs delivering on the value promise

Project

Planned completion

 

Actual Completion

NSW Schools 1

January 2005 

 

January 2005

Queensland Southbank TAFE

December 2008

 

First buildings delivered Jan 2007 Other buildings ahead of schedule

South Australian Police & Courts

December 2006

 

November 2006

The nine facilities were completed on budget and ahead of time

80 days early across nine facilities

Royal Melbourne Showgrounds 

August 2006 

 

August 2006 

Victorian County Court

May 2002

 

May 2002

Casey Hospital

September 2004

 

August 2004

Victorian Correctional Facilities

Correctional Programs Centre - October 2005 Remand Centre - December 2005

Correctional Programs Centre - February 2006 Remand Centre - March 2006

Value for money is one of the key factors for governments pursuing a PPP model to deliver infrastructure. Not only is value for money achievable through time and cost efficiencies, it can also be gained from: greater certainty of expected financial outcomes; innovation and efficiency; and releasing public sector resources to focus on core service delivery. Our survey captured end-user and government contract managers' observations of whether and how the projects are delivering value for money.