Other cost components covered by the Amendment Deed

Work on the tunnel ventilation stack, at just under one million dollars, was the next largest component. The Deed also included some costs for land acquisition. Most of the other costs came from complying with the Conditions of Approval arising from the Supplementary EIS. We have not examined these other costs in detail. Together, they took the remaining 22 per cent of the $38.1 million FAD funds.