4. Were the road changes based on a robust assessment?
>
4.4 Was there a robust evaluation of each proposed road change?
4.4 Was there a robust evaluation of each proposed road change?
More Information
No assurance of robust assessment
Financial viability influenced planning decisions
Harbour Street exit may cause congestion
Access to the Cahill Expressway
Allowing the turn from Cowper Wharf Roadway resulted in $22 million in compensation