2.3 Risk transfer
Outline the risk transfer under the project agreement. The risk allocation matrix, completed during the project procurement phase, will provide a basis for this analysis. A risk summary as in Table 3 may be included.
Table 3 Risk Summary
| Risk | State | Private Party |
| Site risks | √ | |
| Design risk | √ | |
| Construction risk | √ | |
| Commissioning risk | √ | |
| Operating risk | √ | |
| Market risk | √ | |
| Industrial relations | √ | |
| Change in government policy/law | √ | |
| Regulatory change | √ | |
| Force majeure | √ | √ |
| Asset ownership | √ | |
| Inflation post execution | √ | |
| Exchange rate post execution | √ | |
| Interest rate | √ | |
| Financing/refinancing post execution | √ | |
| Sponsor risk | √ | |
| Termination | √ | √ |
| Residual value | √ |