Timing of the Review
Throughout the procurement phase, the PSC may have a number of stages. The QA Review should be conducted prior to government approval of the PSC, which must be before the Request for Proposal is released to bidders. Therefore it is recommended that the QA Review be undertaken at the same time as the Gate 3 Readiness for Service Gateway Review.
If there are material changes to the PSC (+/- 20%) at any stage in the project, it may also be appropriate to conduct a further PSC QA Review.
Website: www.partnerships.vic.gov.au
© Copyright State of Victoria 2009
This publication is copyright. No part may be reproduced by any process except in accordance with the provisions of the Copyright Act 1968.
Published: February 2009
Version 2 published January 2010