The scheduled forecast for FOC has slipped by 18 months from the original plan primarily caused by delays to the development, certification and qualification of the first-of-type aircraft. Schedule recovery is not expected because of the increased scope and complexity of the conversion. Delays will impact the introduction into service of the new MRTT capability and delay achievement of the expected operational readiness.