Schedule Performance - Project Approval to Capability Realisation

The schedule forecast for FOC remains as per the original plan. Major deliveries of vehicles have occurred as noted in the Project Status. The Bushranger Project suffered delays of 8 and 26 months in achieving the In-Service Date and FOC respectively for the first of the three vehicle Production Periods when it experienced a number of technical problems. However the third Production Period is forecast to be on time.