1.6 Project Maturity Score and Benchmark

Maturity Score

Attributes

Schedule

Cost

Requirement

Technical Understanding

Technical Difficulty

Commercial

Operations and support

Total

Project Stage: Preliminary Design Review

Benchmark

6

6

7

6

6

7

7

45

Current Project

7

7

7

7

7

6

6

47

Explanation

■ Commercial: finalisation of block contracts has been delayed. The impending contract signatures will close a significant commercial risk.

■ Operations and Support: support system activities are progressing with planned lead in reviews and the detailed design review for the support system scheduled in 2010.

■ Schedule, cost, technical understanding and technical difficulty attributes are rated higher than the benchmark for this stage.