Review | Major System/ Platform Variant | Original Planned | Current Planned | Achieved/ Forecast | Variance (Months) |
System Functional | AWD Program | Mar 08 |
| Apr 08 | 1 |
Preliminary Design | AWD Program | Dec 08 |
| Feb 09 | (1) |
Critical Design | AWD Program | Dec 09 | Dec 09 | Feb 10 | (1) |
Variance Explanations | Note(1): The PDR was conducted as scheduled in December 2008 and completed as scheduled in February 2009. The CDR is scheduled to be conducted in December 2009 and completed in February 2010. | ||||