Test and Evaluation | Major System/ Platform Variant | Original Planned | Current Planned | Achieved/ Forecast | Variance (Months) |
System Integration | (2) |
|
|
|
|
Acceptance
| Ship 1 - Commencement of Category 5 Trials | Aug 14 | Aug 14 | Aug 14 | 0 |
Ship 1 - Provisional Acceptance | Dec 14 | Dec 14 | Dec 14 | 0 | |
Ship 2 - Commencement of Category 5 Trials | Nov 15 | Nov 15 | Nov 15 | 0 | |
Ship 2 - Provisional Acceptance | Mar 16 | Mar 16 | Mar 16 | 0 | |
Ship 3 - Commencement of Category 5 Trials | Feb 17 | Feb 17 | Feb 17 | 0 | |
Ship 3 - Provisional Acceptance | Jun 17 | Jun 17 | Jun 17 | 0 | |
Variance Explanations | Note(2): The System Integration Test and Evaluation events have not been finalised. They will be finalised following completion of AWD Program Critical Design Review, currently scheduled for February 2010. | ||||