3.1  Design Review Progress

Review

Major System/ Platform Variant

Original Planned

Current Planned

Achieved/ Forecast

Variance (Months)

Software Design

Aircraft software

Feb 08

Feb 08

Feb 08

0

System Requirements

Aircraft

N/A

N/A

N/A

N/A

Automated Maintenance Environment

Oct 08

Oct 08

Oct 08

0

Electronic Warfare data library

Jul 08

Jul 08

Jul 08

0

Tactical Operation Flight Trainers

Oct 08

Oct 08

Oct 08

0

Low Cost Trainers

Oct 08

Oct 08

Oct 08

0

Integrated Visual Environment Maintenance Trainers

Oct 08

Oct 08

Oct 08

0

Preliminary Design

Aircraft

N/A

N/A

N/A

N/A

Automated Maintenance Environment

Nov 08

Nov 08

Nov 08

0

Electronic Warfare data library

Oct 08

Dec 08

Dec 08

2

Tactical Operation Flight Trainers

Note 1

 

 

 

Low Cost Trainers

Note 1

 

 

 

Integrated Visual Environment Maintenance Trainers

Note 1

 

 

 

Critical Design

Aircraft

Jul 08

Sep 08

Sep 08

2

Automated Maintenance Environment

Feb 09

Mar 09

Mar 09

1

Electronic Warfare data library

Dec 08

Mar 09

May 09

5

Tactical Operation Flight Trainers

Apr 09

Apr 09

Apr 09

0

Low Cost Trainers

Apr 09

Apr 09

Apr 09

0

Integrated Visual Environment Maintenance Trainers

Jan 09 - Oct 09

Jan 09 - Oct 09

Jan 09 - Oct 09

0

Variance Explanations

■  No Aircraft Systems Requirement Review or Preliminary Design Review for the project as the aircraft is a MOTS design.

■  The Aircraft Critical Design Review was delayed due to the Instrument landing System integration requiring re-design.

■  The Electronic Warfare data library preliminary design review was delayed due to the US Navy adopting a new design process, and the issue of classified data being unable to be released

■  The Critical Design Review for the Automated Maintenance Environment slipped by one week.

■  The Integrated Visual Environment Maintenance Trainers follow a spiral development path with several combined Preliminary/Critical Design Reviews beginning in January 2009 and continuing through until October 2009.

Note 1: Preliminary and Critical Design Reviews were combined to meet delivery targets.