Test and Evaluation | Major System/ Platform Variant | Original Planned | Current Planned | Achieved/ Forecast | Variance (Months) |
System Integration | Instrument Landing System antennae qualification | Jul 08 | Apr 09 | May 09 | 10 |
Instrument Landing System - Aircraft Integration Test | Jan 09 - Mar 09 | Mar 09 - Apr 09 | May 09 - June 09 | 3 | |
Aircraft software integration | Mar 09 - Jul 09 | Mar 09 - Dec 09 | Mar 09 - Dec 09 | 5 | |
Electronic Warfare data library | Mar 09 | Oct 09 |
| 7 | |
Automated Maintenance Environment | Aug 09 | Aug 09 | Aug 09 | 0 | |
Acceptance | 1st Aircraft Production Test (Boeing) | Jul 09 | Jul 09 | Jul 09 | 0 |
| Aircraft Post-Production Test and Evaluation (US Navy) | Jul 09 - Oct 09 | Jul 09 - Dec 09 | Jul 09 - Dec 09 | 2 |
| Electronic Warfare data library | May 09 | Dec 09 | Dec 09 | 7 |
| Automated Maintenance Environment | Aug 09 | Aug 09 | Aug 09 | 0 |
Variance Explanations | ■ Instrument Landing System antennae qualification and integration tests delayed due to a test failures of the antennas and the need to redesign. ■ Airframe Integration Test - Slip due to failure of Instrument Landing System antennae, ■ Software Integration - classified. ■ The Electronic Warfare data library testing was delayed due to the US Navy adopting a new design process, and the continuing issue of classified data being unable to be released. ■ Post-production test and evaluation affected by the delays in the instrumented landing system qualification and aircraft software integration. | ||||