1.6  Project Maturity Score and Benchmark

Maturity Score

Attributes

Total

Scheduled

Cost

Requirement

Technical Understanding

Technical Difficulty

Commercial

Operations and Support

Project Stage: Acceptance Testing

Benchmark

8

8

8

8

9

8

8

57

Current Project

10

8

8

8

8

8

7

57

Explanation

  Schedule: The first two MRH aircraft and support systems were accepted into service.

  Technical Difficulty: MRH is between "Integrated" and "Tested", as MRH is yet to achieve complete acceptance testing on all systems and sub-systems.

  Operations and Support: While elements of system support are defined and procurement is occurring, MRH have yet to reach the point where all elements are procured and ready for integration into the support system.