Date | Amount | Factor | Explanation |
Aug 04 | 953.9 | Scope | Second Pass Approval. |
Jun 06 | 2,565.5 | Scope | Incorporation of Air 9000 Phase 4 (Black Hawk Upgrade/Replacement) and Air 9000 Phase 6 (Maritime Support Helicopter). |
Oct 06 | (219.0) | Transfer | The funding relates to facilities elements of the project that will be managed by DSG. |
Oct 08 | (20.0) | Transfer | Transfer to DSG for Facilities Infrastructure. |
Oct 08 | 31.5 | Scope | RCI is funding for Full Flight and Mission Simulator Facilities. |
Total | 3,311.9 | Real Variation |
|