3.1  Design Review Progress

Review

Major System/ Platform Variant

Original Planned

Current Planned

Achieved/ Forecast

Variance (Months)

System Requirements

MRH aircraft - Phase 2

Aug 05

Oct 05

Sep 05

1

MRH aircraft - Phase 4/6

Apr 07

Apr 07

May 07

1

MRH Software Support Centre

N/A

Mar 07

Apr 07

1

Electronic Warfare Self Protection Support System

N/A

N/A

Nov 05

N/A

Ground based Mission planning and Management System

Oct 05

Oct 05

Feb 07

16

MRH Instrumented System

N/A

Jun 07

Jul 07

1

Preliminary Design

MRH aircraft - Phase 2

Jan 06

Jan 06

Apr 06

3

MRH aircraft - Phase 4/6

N/A

N/A

Jun 08(2)

N/A

MRH Software Support Centre

N/A

Jun 07

Jun 07

0

Electronic Warfare Self Protection Support System

Mar 06

Mar 06

May 06

2

Ground based Mission planning and Management System

Jul 06

Apr 07

Jun 07

11

MRH Instrumented System

N/A

Jun 07

Jul 07

1

Critical Design

MRH aircraft - Phase 2

May 06

May 06

Jun 06

1

MRH aircraft - Phase 4/6

Aug 08

N/A

Oct 08(2)

2

MRH Software Support Centre

N/A

Oct 07

Sep 07

(1)

Electronic Warfare Self Protection Support System

Sep 06

Sep 06

Oct 06

1

Ground based Mission planning and Management System

Nov 06

Nov 07

Jul 08

20

MRH Instrumented System

N/A

Jun 08

Jun 08

0

Variance Explanations

Delays in the Systems Engineering process have resulted from the developmental nature of the aircraft system, with the MRH90 variant being unique in some ways.

Note 2: All elements of the Phase 4/6 requirements with the exception of the Pintle Machine Gun Mount (PMGM) were completed on these dates. The PMGM requirements are in the process of being removed from the general Phase 4/6 systems engineering process and a dedicated PMGM systems engineering process is being separately developed with the contractor.