Review | Major System/ Platform Variant | Original Planned | Current Planned | Achieved/ Forecast | Variance (Months) |
System Requirements | MRH aircraft - Phase 2 | Aug 05 | Oct 05 | Sep 05 | 1 |
MRH aircraft - Phase 4/6 | Apr 07 | Apr 07 | May 07 | 1 | |
MRH Software Support Centre | N/A | Mar 07 | Apr 07 | 1 | |
Electronic Warfare Self Protection Support System | N/A | N/A | Nov 05 | N/A | |
Ground based Mission planning and Management System | Oct 05 | Oct 05 | Feb 07 | 16 | |
MRH Instrumented System | N/A | Jun 07 | Jul 07 | 1 | |
Preliminary Design | MRH aircraft - Phase 2 | Jan 06 | Jan 06 | Apr 06 | 3 |
MRH aircraft - Phase 4/6 | N/A | N/A | Jun 08(2) | N/A | |
MRH Software Support Centre | N/A | Jun 07 | Jun 07 | 0 | |
Electronic Warfare Self Protection Support System | Mar 06 | Mar 06 | May 06 | 2 | |
Ground based Mission planning and Management System | Jul 06 | Apr 07 | Jun 07 | 11 | |
MRH Instrumented System | N/A | Jun 07 | Jul 07 | 1 | |
Critical Design | MRH aircraft - Phase 2 | May 06 | May 06 | Jun 06 | 1 |
MRH aircraft - Phase 4/6 | Aug 08 | N/A | Oct 08(2) | 2 | |
MRH Software Support Centre | N/A | Oct 07 | Sep 07 | (1) | |
Electronic Warfare Self Protection Support System | Sep 06 | Sep 06 | Oct 06 | 1 | |
Ground based Mission planning and Management System | Nov 06 | Nov 07 | Jul 08 | 20 | |
MRH Instrumented System | N/A | Jun 08 | Jun 08 | 0 | |
Variance Explanations | Delays in the Systems Engineering process have resulted from the developmental nature of the aircraft system, with the MRH90 variant being unique in some ways. Note 2: All elements of the Phase 4/6 requirements with the exception of the Pintle Machine Gun Mount (PMGM) were completed on these dates. The PMGM requirements are in the process of being removed from the general Phase 4/6 systems engineering process and a dedicated PMGM systems engineering process is being separately developed with the contractor. | ||||