Item | Original Planned | Achieved/ Forecast | Variance (Months) | Variance Explanations/ Implications |
IOC (Navy) | Jul 10 | Jul 10 | 0 | N/A |
IOC (Army) | Apr 11 | Oct 11 | 6 | The MRH Project Management Stakeholder Group agreed to the declaration of a likely program delay of "up to six months to the IOC (Army) milestone". This potential delay is being closely managed with the aim being to minimise any delay to this program. It is assessed that this potential delay will not effect the achievement of any of the other MRH90 capability milestones. |