1.6 Project Maturity Score and Benchmark

Maturity Score

Attributes

Total

Schedule

Cost

Requirement

Technical Understanding

Technical Difficulty

Commercial

Operations and Support

Project Stage: Critical Design Review

Benchmark

7

7

7

8

7

7

7

50

Current Project

5

7

7

8

7

6

7

47

Explanation

Schedule: Boeing currently plans to deliver a fully capable aircraft in March 2010, 40 months later than contract baseline.

Commercial: The Commonwealth assesses that there are significant risks to Boeing's delivery plans.