Description | Remedial Action |
The major risks to the project fall within the following categories: ■ Schedule; and ■ Attainment of contracted technical performance. Schedule and technical performance risks arise from lack of technical maturity of key on-board sensor systems, incomplete software development, system integration and acceptance testing. | Engage and influence the prime contractor and major sub-contractors to maintain appropriate focus and commitment to deliver contracted performance to a credible and resourced schedule. Exercise contractual remedies. |