Description | Remedial Action |
Current major project issues fall within the following categories: ■ Technical performance short falls; ■ Schedule delays; and ■ Contract management. Technical performance shortfalls arise due to some sub-systems not meeting contracted performance requirements. Notwithstanding significant progress made in the acceptance test phase, schedule delays continue to be encountered. Contract management issues relate to : ■ Schedule delays arising out of problems associated with subsystem maturity and stability and integrated system performance. ■ Finalisation of In Service Support Contract. | Engage and influence the prime contractor and major sub-contractors to maintain appropriate focus and commitment to deliver contracted performance to a credible and resourced schedule. Adopt 'Incremental' delivery approach.Exercise contractual remedies. Maintain engagement with the prime contractor to achieve alignment of in-service support with the delivery of the first aircraft and associated support equipment. |