Date | Amount | Factor | Explanation |
Aug 04 | (0.1) | Budgetary Adjustment | Administration Savings harvest. |
Sep 04 | 4.8 | Scope | To fund a risk reduction activity for the Project to obtain design data and develop designs to meet Australian essential requirements. |
Nov 05 | 29.6 | Scope | First pass Approval. |
Nov 07 | 2,920.8 | Scope | Project received Second Pass approval to acquire two Amphibious Ships that will provide the ADF with increased amphibious deployment and sustainment capability to support an enhanced deployed force. |
Oct 08 | 9.4 | Transfer | Transfer of funding for technical studies from DSTO. |
Total | 2,964.5 | Real Variation |
|