3.1  Design Review Progress

Review

Major System/ Platform Variant

Original Planned

Current Planned

Achieved/ Forecast

Variance (Months)

System Requirements

Mission System (Includes Platform / Combat Systems)

Feb 08

Feb 08

Feb 08

0

Support System

Apr 08

Apr 08

Apr 08

0

Preliminary Design

Communication

Oct 08

Oct 08

Dec 08

2

Navigation

Oct 08

Oct 08

Dec 08

2

Platform System

Nov 08

Nov 08

Nov 08

0

Combat System

Dec 08

Apr 09

Apr 09

4

Whole of Ship

Jan 09

May 09

May 09

4

Support system

Mar 09

May 09

May 09

2

Detailed Design

Communication

May 09

Sep 09

Sep 09

4

Navigation

Jun 09

Jun 09

Jun 09

0

Platform system

Jun 09

Jun 09

Jun 09

0

Combat system

Jul 09

Oct 09

Oct 09

3

Whole of ship

Jul 09

Nov 09

Nov 09

4

Support system

Aug 09

Dec 09

Dec 09

4

Variance Explanations

Due to the complexity of the integration of the combat, communications and platform systems, more time has been allocated to the design review activities. The construction of main hull sections commenced this year as planned. Construction of the superstructure, where many of the integration issues reside, is not planned to commence until June 2010 and the deferred Design Reviews are unlikely to affect the construction schedule and final delivery date.