Review | Major System/ Platform Variant | Original Planned | Current Planned | Achieved/ Forecast | Variance (Months) |
System Requirements | Mission System (Includes Platform / Combat Systems) | Feb 08 | Feb 08 | Feb 08 | 0 |
Support System | Apr 08 | Apr 08 | Apr 08 | 0 | |
Preliminary Design | Communication | Oct 08 | Oct 08 | Dec 08 | 2 |
Navigation | Oct 08 | Oct 08 | Dec 08 | 2 | |
Platform System | Nov 08 | Nov 08 | Nov 08 | 0 | |
Combat System | Dec 08 | Apr 09 | Apr 09 | 4 | |
Whole of Ship | Jan 09 | May 09 | May 09 | 4 | |
Support system | Mar 09 | May 09 | May 09 | 2 | |
Detailed Design | Communication | May 09 | Sep 09 | Sep 09 | 4 |
Navigation | Jun 09 | Jun 09 | Jun 09 | 0 | |
Platform system | Jun 09 | Jun 09 | Jun 09 | 0 | |
Combat system | Jul 09 | Oct 09 | Oct 09 | 3 | |
Whole of ship | Jul 09 | Nov 09 | Nov 09 | 4 | |
Support system | Aug 09 | Dec 09 | Dec 09 | 4 | |
Variance Explanations | Due to the complexity of the integration of the combat, communications and platform systems, more time has been allocated to the design review activities. The construction of main hull sections commenced this year as planned. Construction of the superstructure, where many of the integration issues reside, is not planned to commence until June 2010 and the deferred Design Reviews are unlikely to affect the construction schedule and final delivery date. | ||||