3.2  Contractor Test and Evaluation Progress

Test and Evaluation

Major System/ Platform Variant

Original Planned

Current Planned

Achieved/ Forecast

Variance (Months)

System Integration

LHD Ships #1 and 2

Mar 15

Mar 15

Mar 15

0

Acceptance

LHD Ship#1 Project Acceptance

Jan 14

Jan 14

Jan 14

0

LHD Ship#2 Project Acceptance

Aug 15

Aug 15

Aug 15

0

LHD Final Acceptance

Sep 15

Sep 15

Sep 15

0

Variance Explanations

N/A