Maturity Score | Attributes | Total | |||||||
Schedule | Cost | Requirement | Technical Understanding | Technical Difficulty | Commercial | Operations and Support | |||
Project Stage: System Integration & Test | Benchmark | 7 | 8 | 8 | 8 | 8 | 8 | 8 | 55 |
Current Project | 9 | 7 | 8 | 7 | 8 | 7 | 9 | 55 | |
Explanation | Schedule: In Service Date achieved in December 2004 with remainder of schedule well understood. Cost: Some risks are yet to be retired that may require access to contingency budget allocations. Estimate at Completion within Project approvals. Requirement: Integration and testing has verified achievement of the majority of the endorsed requirements. Technical Understanding: Not all logistics data and arrangements have been delivered to support current and future capability. Technical Difficulty: System integration and acceptance testing nearing completion. Performance issues understood. Commercial: Contractor performance is satisfactory but improvement is required in order to ensure critical milestone achievement. Operations and Support: ARH System elements have commenced transition to In-Service Managers. | ||||||||