1.6  Project Maturity Score and Benchmark

Maturity Score

Attributes

Total

Schedule

Cost

Requirement

Technical Understanding

Technical Difficulty

Commercial

Operations and Support

Project Stage: System Integration & Test

Benchmark

7

8

8

8

8

8

8

55

Current Project

9

7

8

7

8

7

9

55

Explanation

Schedule: In Service Date achieved in December 2004 with remainder of schedule well understood.

Cost: Some risks are yet to be retired that may require access to contingency budget allocations. Estimate at Completion within Project approvals.

Requirement: Integration and testing has verified achievement of the majority of the endorsed requirements.

Technical Understanding: Not all logistics data and arrangements have been delivered to support current and future capability.

Technical Difficulty: System integration and acceptance testing nearing completion. Performance issues understood.

Commercial: Contractor performance is satisfactory but improvement is required in order to ensure critical milestone achievement.

Operations and Support: ARH System elements have commenced transition to In-Service Managers.