Test and Evaluation | Major System/ Platform Variant | Original Planned | Current Planned | Achieved/ Forecast | Variance (Months) |
System Integration | Full Flight and Mission Simulator Contractor In-plant | Jul 04 |
| Oct 07 | 39 |
Cockpit Procedures Trainer Oakey Contractor In-plant and On-Site | Jul 04 |
| Jun 08 | 47 | |
Cockpit Procedures Trainer Darwin Contractor In-plant and Army In-plant | Jul 04 | Jan 09 | Dec 08 | 53 | |
Acceptance | |||||
Type Acceptance Review Special Flight Permit | Oct 04 |
| Jun 05 | 8 | |
Australian Military Type Certificate | Jun 05 |
| Oct 05 | 4 | |
Aircrew Training Devices - Final Acceptance Test and Evaluation | |||||
Full Flight and Mission Simulator (Transition Training capability) | Feb 05 |
| Nov 07 | 33 | |
Full Flight and Mission Simulator (Full Training capability) | Feb 05 | Dec 09 | Nov 09 | 57 | |
Cockpit Procedures Trainer Oakey | Feb 05 | Jan 10 | Jan 10 | 59 | |
Cockpit Procedures Trainer Darwin | Feb 05 | Feb 10 | Apr 10 | 62 | |
Acceptance | |||||
ARH #11 | Jul 06 |
| Apr 08 | 21 | |
ARH #22 | Apr 08 | Sep 10 | Sep 10 | 29 | |
Variance Explanations | The Current Planned dates are those agreed with the Contractor, Australian Aerospace, during the Dispute resolution process and consequential approved Contract Change Proposal and form the Payment Milestones under the rebaselined Acquisition Contract. The Contractor is managing the delivery of the remaining Acquisition Contract capability Milestones in accordance with the Integrated Master Schedule. All 22 ARH are systematically being upgraded through a retrofit program in order to bring them up to the contracted specification at no additional cost to the Commonwealth. The retrofit program is complex requiring aircraft components to be removed and cycled through an upgrade program with the Original Equipment Manufacturer before being re-fitted to an aircraft. Currently the acceptance of the 22nd ARH is expected to be achieved in September 2010. Aircrew Training Devices The Full Flight and Mission Simulator Contractor In-Plant Test and Evaluation achievement date reported in the 2007/08 reported that Contractor In-Plant Test and Evaluation was initially conducted in France in late 2005 however, testing only verified approximately 20% of the contacted requirement. Further testing was completed in October 2007 following the device's shipment from France and installation at Oakey with the Commonwealth accepting the device as fit for transition training in December 2007. The Full Flight and Mission Simulator has been upgraded to the final aircraft configuration and is on track to have its accreditation and recurrent fidelity checks completed in accordance with the agreed rebaselined Acquisition Contract milestone schedule. | ||||