Date | Amount | Factor | Explanation |
Jun 04 | (149.4) | Budgetary Adjustment | Defence Capability direction re currency mix at approval and Government decisions. |
Aug 04 | (1.2) | Budgetary Adjustment | Administrative Savings harvest. |
Aug 05 | (3.0) | Budgetary Adjustment | Skilling Australia's Defence Industry harvest. |
Nov 05 | (135.5) | Transfer | Transfer to DSG for delivery of MRTT infrastructure at RAAF Amberley and at other RAAF bases. |
Total | (289.1) | Real Variation |
|