2.5  End of Financial Year Total Project Expenditure Variance Attribution

Variance

Variance Factor

Explanation

(0.2)

FMS

Variation in payments is due to schedule delay, pushing requirement out to Financial Year 2009/10.

(0.1)

Overseas Industry

Variation in payments is due to delay in invoicing.

(0.3)

Total Variance