Test and Evaluation | Major System/ Platform Variant | Original Planned | Current Planned | Achieved/ Forecast | Variance (Months) |
System Integration | MRTT Aircraft | Aug 08 | Dec 08 | Mar 10 | 19 |
Simulation Devices | Feb 09 | Dec 09 | Dec 10 | 22 | |
Acceptance | MRTT Aircraft | Dec 08 | Feb 09 | Jun 10 | 18 |
Simulation Devices and Simulation Devices Facility | May 09 | Jan 10 | Apr 11 | 23 | |
Full Mission Simulator Final Accreditation | Feb 10 | May 10 | Oct 11 | 20 | |
Variance Explanations | System Integration Test & Evaluation is ongoing for the first-of-type MRTT Aircraft. Originally planned as a single-phase activity, the test program was split into two phases to accommodate changes to the Remote Aerial Refuelling Operator console (as described above). The first phase, for civil certification of the modified aircraft, was successfully completed in February 2008. The second phase, for military certification and qualification of the modified aircraft commenced end of December 2008, approximately six months late due to the combination of delays to the first and second conversion phases. Acceptance Test & Evaluation of the first MRTT Aircraft will be conducted as part of the Customer Acceptance Process following completion of all system integration testing and aircraft preparation for delivery. Delays to completion of the MRTT Aircraft test process has a knock-on impact to completion of testing of the Simulation Devices. | ||||