3.3  Progress toward Initial Operational Capability

Item

Original Planned

Achieved/ Forecast

Variance (Months)

Variance Explanations/ Implications

MRTT

Dec 09

Late 2010 / Early 2011

12

Delay to achievement of Initial Operational Capability is due to delays to the development, certification and qualification of the first-of-type aircraft. Some schedule is expected to be recovered through the return of the second aircraft to Madrid (following conversion in Australia) for conduct of training and additional test activities. Delays will require alternative arrangements for provision of aerial refuelling services to meet Air Force operational and training commitments.