3.2  Contractor Test and Evaluation Progress

Test and Evaluation

Major System/ Platform Variant

Original Planned

Current Planned

Achieved/ Forecast

Variance (Months)

System Integration

C-17 Globemaster III Aircraft

(2)

 

 

 

Simulated Avionics

 

Jul 08

Jan 10

18

Acceptance

C-17 Globemaster III Aircraft A41-206

 

Nov 06

Nov 06

0

C-17 Globemaster III Aircraft A41-207

 

May 07

May 07

0

C-17 Globemaster III Aircraft A41-208

 

Feb 08

Dec 07

(2)

C-17 Globemaster III Aircraft A41-209

 

Mar 08

Jan 08

(2)

Australian Visual Database On Site Review

 

Oct 09

Oct 09

0

Weapon System Trainer

 

Dec 09

Dec 09

0

Virtual Cargo Load Model

 

Jul 08

Oct 08

3

Variance Explanations

Note 2: C-17 Globemaster III Aircraft Developmental Test & Evaluation (DT&E) not required as it is Military Off-The-Shelf i.e. Mature Design with no ADF unique changes.

Simulated Avionics DT&E - Sub-contractor Intellectual Property issues resulted in delay in Simulated Instruments integration, although no delay is anticipated in overall Aircrew Simulator delivery date.

Aircraft A41-208 and A41-209 were completed early by the manufacturer (Boeing).