Test and Evaluation | Major System/ Platform Variant | Original Planned | Current Planned | Achieved/ Forecast | Variance (Months) |
System Integration | C-17 Globemaster III Aircraft | (2) |
|
|
|
Simulated Avionics |
| Jul 08 | Jan 10 | 18 | |
Acceptance | C-17 Globemaster III Aircraft A41-206 |
| Nov 06 | Nov 06 | 0 |
C-17 Globemaster III Aircraft A41-207 |
| May 07 | May 07 | 0 | |
C-17 Globemaster III Aircraft A41-208 |
| Feb 08 | Dec 07 | (2) | |
C-17 Globemaster III Aircraft A41-209 |
| Mar 08 | Jan 08 | (2) | |
Australian Visual Database On Site Review |
| Oct 09 | Oct 09 | 0 | |
Weapon System Trainer |
| Dec 09 | Dec 09 | 0 | |
Virtual Cargo Load Model |
| Jul 08 | Oct 08 | 3 | |
Variance Explanations | Note 2: C-17 Globemaster III Aircraft Developmental Test & Evaluation (DT&E) not required as it is Military Off-The-Shelf i.e. Mature Design with no ADF unique changes. Simulated Avionics DT&E - Sub-contractor Intellectual Property issues resulted in delay in Simulated Instruments integration, although no delay is anticipated in overall Aircrew Simulator delivery date. Aircraft A41-208 and A41-209 were completed early by the manufacturer (Boeing). | ||||