3.2  Contractor Test and Evaluation Progress

Review

Major System/ Platform Variant

Original Planned

Current Planned

Achieved/ Forecast

Variance (Months)

System Integration

Phase 2.1

N/A

N/A

N/A

N/A

Phase 2.2 (First Article Contract / Project acceptance)

Feb 05

Jan 05

Jan 05

(1)

Phase 2.3 (System Integration Lab Test)

May 07

May 07

May 07

0

HACTS (Factory Acceptance Test)

May 06

May 06

May 06

0

Acceptance

Phase 2.1

N/A

N/A

N/A

N/A

Phase 2.2 (Aircraft Modification DMO Acceptance - A&B model)

Nov 05

Nov 05

Nov 05

0

Phase 2.3 (Aircraft Verification and Validation)

Sep 08

Sep 08

Aug 08

(1)

HACTS (Site Acceptance Test)

Jun 06

Jun 06

Jun 06

0

Variance Explanations

Modification of Validation and Verification aircraft completed earlier than anticipated.