Review | Major System/ Platform Variant | Original Planned | Current Planned | Achieved/ Forecast | Variance (Months) |
System Integration | Phase 2.1 | N/A | N/A | N/A | N/A |
Phase 2.2 (First Article Contract / Project acceptance) | Feb 05 | Jan 05 | Jan 05 | (1) | |
Phase 2.3 (System Integration Lab Test) | May 07 | May 07 | May 07 | 0 | |
HACTS (Factory Acceptance Test) | May 06 | May 06 | May 06 | 0 | |
Acceptance | Phase 2.1 | N/A | N/A | N/A | N/A |
Phase 2.2 (Aircraft Modification DMO Acceptance - A&B model) | Nov 05 | Nov 05 | Nov 05 | 0 | |
Phase 2.3 (Aircraft Verification and Validation) | Sep 08 | Sep 08 | Aug 08 | (1) | |
HACTS (Site Acceptance Test) | Jun 06 | Jun 06 | Jun 06 | 0 | |
Variance Explanations | Modification of Validation and Verification aircraft completed earlier than anticipated. | ||||