4.1  Major Project Risks

 

Description

Remedial Action

Phase 2.1

There are no outstanding risks associated with this sub phase as it is technically complete.

N/A

Phase 2.2

There are no outstanding risks associated with this sub phase as it is technically complete.

N/A

Phase 2.3

There is a chance that the upgraded F/A-18 A/B Electronic Warfare system will be affected by the inability to adequately test the Electronic Warfare threat libraries leading to an impact on safety.

Phase 2.3 Ground Systems Manager to develop a Memorandum Of Understanding with Airborne Self Protection Systems Program Office to purchase a new simulator and to identify lower level activities.

There is a chance that the F/A-18 A/B Operational Flight Program test program will be affected by the late delivery of the first F/A-18 Electronic Counter Measures jammer pod leading to an impact on schedule and performance.

Closely monitor Elta System's progress in delivering the F/A-18 Electronic Counter Measures jammer pod.

HACTS

There is a chance that Australian Unique Software Loads will not be compatible with HACTS leading to an impact on performance project cost and schedule.

HACTS Program Office is developing mitigation strategies with Key Stakeholders to address the risk and enable future loading of Australian Unique Software Loads.

There is a chance that HACTS capability will not be optimised and/or rectified leading to an impact on performance, cost and schedule.

HACTS Program Office and Prime contractor are developing a Common Identification Document to capture all Air Combat Group Issues and activities of concern. This document will enable all parties to communicate and prioritise treatment of any known risks.