Date | Amount | Factor | Explanation |
Nov 98 | (0.1) | Budgetary Adjustment | Overseas travel not required. |
Jul 99 | (152.6) | Transfer | Transfer to Project Sea 1428 Ph 2A for the procurement of Evolved Sea Sparrow missiles on behalf of Sea 1390 Phase 2. |
Aug 04 | (0.7) | Budgetary Adjustment | Administrative Savings harvest. |
Total | (153.4) | Real Variation |
|