2.2  Project Real Variation History Explanation

Date

Amount

Factor

Explanation

Nov 98

(0.1)

Budgetary Adjustment

Overseas travel not required.

Jul 99

(152.6)

Transfer

Transfer to Project Sea 1428 Ph 2A for the procurement of Evolved Sea Sparrow missiles on behalf of Sea 1390 Phase 2.

Aug 04

(0.7)

Budgetary Adjustment

Administrative Savings harvest.

Total

(153.4)

Real Variation