Review | Major System/ Platform Variant | Original Planned | Current Planned | Achieved/ Forecast | Variance (Months) |
System Integration | HMAS Sydney | Dec 02 | Sep 05 | Sep 05 | 33 |
HMAS Melbourne | Jul 03 | Feb 07 | Jun 07 | 47 | |
HMAS Darwin | Feb 04 | Feb 08 | May 08 | 51 | |
HMAS Newcastle | Jul 04 | Feb 09 | Feb 09 | 55 | |
Provisional Acceptance | HMAS Sydney | May 03 | Dec 06 | Dec 06 | 43 |
HMAS Melbourne | Jan 04 | Oct 07 | Oct 07 | 45 | |
HMAS Darwin | Jul 04 | Aug 08 | Aug 08 | 49 | |
HMAS Newcastle | Jan 05 | Jun 09 | May 09 | 52 | |
Team Trainer | Apr 02 | Feb 07 | Nov 07 | 67 | |
Warfare Systems Support Centre | Apr 04 | Nov 08 | Nov 08 | 55 | |
Acceptance | HMAS Sydney | Apr 04 | Nov 08 | Nov 08 | 55 |
HMAS Melbourne | Sep 04 | Nov 08 | Dec 08 | 51 | |
HMAS Darwin | Mar 05 | Nov 08 | Nov 08 | 44 | |
HMAS Newcastle | Sep 05 | Dec 09 | Dec 09 | 51 | |
Team Trainer | Sep 06 | Dec 09 | Dec 09 | 39 | |
Warfare Systems Support Centre | Sep 06 | Dec 09 | Dec 09 | 39 | |
Variance Explanations | Schedule delays to this program have resulted from the program complexity being underestimated from the outset. Two schedule re-baseline activities have been required; the latest as Contract Change Proposal 255, which encompassed: ■ the Commonwealth partial termination for convenience of the Upgrade of HMA Ships Adelaide and Canberra; ■ settlement of an Australian Defence Industry Ltd HMAS Sydney delay claim; ■ a revised viable contract master schedule with a Contract Final Acceptance of December 2009 but within the variable fixed price; ■ improved payment terms going forward; and ■ more certainty in the process and criteria for contract Provisional Acceptance whilst maintaining Australian Defence Industry Ltd, trading as Thales Australia, capability upgrade contract obligations for the remaining program. Contract Change Proposal 255, signed in May 2006, closed out a major contract renegotiation effort. This has assisted in achieving performance improvements against the contract. Further schedule adjustment to project end date has not been required. | ||||