Item | Original Planned | Achieved/ Forecast | Variance (Months) | Variance Explanations/ Implications |
HMAS Sydney | May 03 | Apr 09 | 71 | A three phased 'incremental' approach for Initial Operational Release and Operational Release has been agreed by the DMO and Navy as the most pragmatic means by which to bring the FFG class to full operational employment. Program complexity issues were addressed in preparation for Contractual Acceptance for HMA Ships Sydney, Darwin and Melbourne in November / December 2008. |
HMAS Melbourne | Jan 04 | Apr 09 | 63 | |
HMAS Darwin | Jul 04 | Apr 09 | 57 | |
HMAS Newcastle | Jan 05 | Aug 09 | 55 | HMAS Newcastle achieved Provisional Acceptance in May 2009. It is intended that Initial Operational Release will be coincident with Sydney, Darwin and Melbourne at Initial Operational Release Phase 2. |