Item | Original Planned | Achieved/ Forecast | Variance (Months) | Variance Explanations/ Implications |
HMAS Sydney | Jul 04 | Dec 09 | 65 | A three phased 'incremental' approach for Initial Operational Release and Operational Release has been agreed by the DMO and Navy as the most pragmatic means by which to bring the FFG class to full operational employment |
HMAS Melbourne | Dec 04 | Dec 09 | 60 | |
HMAS Darwin | Jun 05 | Dec 09 | 54 | |
HMAS Newcastle | Dec 05 | Dec 09 | 48 |