3.2  Contractor Test and Evaluation Progress

Review

Major System/ Platform Variant

Original Planned

Current Planned

Achieved/ Forecast

Variance (Months)

System Integration

SRP1D Prototype Modifications - DMO Acceptance

Jan 06

N/A

Jan 06

0

SRP2 Prototype Modifications - DMO Acceptance

Dec 07

N/A

Feb 08

2

Acceptance

N/A

N/A

N/A

N/A

N/A

Variance Explanations

The first SRP2 prototype aircraft was delayed by two months due to emergent issues discovered during prototype rebuild.