Maturity Score |
Attributes |
Total |
|||||||
|
Schedule |
Cost |
Requirement |
Technical Understanding |
Technical Difficulty |
Commercial |
Operations and Support |
|||
|
Project Stage: Acceptance Into Service |
Benchmark |
8 |
8 |
8 |
8 |
9 |
8 |
8 |
57 |
|
Current Project |
8 |
8 |
8 |
8 |
9 |
8 |
8 |
57 |
|
|
Explanation |
The maturity score has not changed as it is now based PP3 which includes a new variant, development of a Protected Mobility Vehicle trailer, the replacement communications harness and acceptance testing. |
||||||||