Review | Major System/ Platform Variant | Original Planned | Current Planned | Achieved/ Forecast | Variance (Months) |
System Requirements | Troop Vehicle | N/A |
| Aug 03 | N/A |
Assault Pioneer Vehicle | N/A |
| Oct 06 | N/A | |
Command Vehicle | N/A |
| Jan 06 | N/A | |
Mortar Vehicle | N/A |
| Feb 09 | N/A | |
Direct Fire Weapon Vehicle | N/A |
| Feb 09 | N/A | |
Ambulance Vehicle | N/A |
| Feb 09 | N/A | |
Preliminary Design | Troop Vehicle | Oct 99 |
| Oct 99 | 0 |
Assault Pioneer Vehicle | Nov 99 |
| Feb 00 | 3 | |
Command Vehicle | Oct 99 |
| Oct 99 | 0 | |
Mortar Vehicle | May 03 |
| Mar 03 | (2) | |
Direct Fire Weapon Vehicle | May 03 |
| Mar 03 | (2) | |
Ambulance Vehicle | Jul 03 |
| May 03 | (2) | |
Critical Design | Troop Vehicle System Verification Review | Oct 02 |
| Sep 02 | (1) |
Assault Pioneer Vehicle Initial Production Vehicle Review | Oct 04 |
| Dec 06 | 26 | |
Command Vehicle Initial Production Vehicle Review | Oct 04 |
| Mar 06 | 17 | |
Mortar Vehicle Initial Production Vehicle Review | Apr 06 |
| May 07 | 13 | |
Direct Fire Weapon Vehicle Initial Production Vehicle Review | Apr 06 |
| Apr 07 | 12 | |
Ambulance Vehicle System Verification Review | Oct 05 |
| Feb 07 | 16 | |
Variance Explanations | Initial testing of the first variant revealed a number of deficiencies against the specification that required rectification and design changes prior to acceptance and production. This had a consequential effect on the system and design review progress for the subsequent variants. As a result additional testing was required which impacted on completing critical design review and contractor test and evaluation. | ||||