3.4  Progress toward Final Operational Capability

Item

Original Planned

Achieved/ Forecast

Variance (Months)

Variance Explanations/ Implications

FOC - PP1

Oct 07

Dec 09

26

Communications harness equipment not available until late 2009 and will be required to be retrofitted to the vehicles before issue to Army.

FOC - PP2

Apr 09

Apr 10

12

FOC - PP3

Apr 12

Apr 12

0

N/A