4.2  Major Project Issues

Description

Remedial Action

The unavailability of communications wiring harness has affected the release of Protected Mobility Vehicles to Army leading to an impact on schedule and cost.

An alternative communications harness is being procured.

The construction of project direct funded facilities has been affected by construction delays leading to an impact on cost and schedule.

DSG, as the agency responsible for all facilities construction, is providing the project with regular updates on the status of the project funded facilities they are managing.

Substantial delays in the processing and implementation of Engineering Change Proposals by the original equipment manufacturer are impacting on schedule and supportability.

Engagement with the original equipment manufacturer is conducted on a regular basis to advance the status of all Engineering Change Proposals and set priorities for implementation.

The capability of the Protected Mobility Vehicle is being impacted by the reduced number of headset being provided with the alternative communications harness leading to an impact on performance.

Additional headsets will be procured to meet capability requirements.