1.6 Project Maturity Score and Benchmark
| Maturity Score | Attributes | Total | |||||||
| Schedule | Cost | Requirement | Technical Understanding | Technical Difficulty | Commercial | Operations and Support | |||
| Project Stage: System Integration & Test | Benchmark | 7 | 8 | 8 | 8 | 8 | 8 | 8 | 55 |
| Current Project | 6 | 7 | 8 | 9 | 8 | 7 | 9 | 54 | |
| Explanation | Schedule: Delivery of Fixed Network Final System Capability is well behind original project schedule, but is being closely managed. Cost: Some cost risk (within bounds of contingency) remains until upgrades to in-scope Mobile platforms are finalised. Technical Understanding: Core system has been accepted by Defence and has been supporting ADF operations since late 2004. Current stage is to deliver improvement and enhanced capabilities. Commercial: Customer working relationship is very good but commercial/contractual issues continue to arise. Operations and Support: Core system has been operational and supported since late 2004. Final system is currently undergoing integration and test. | ||||||||