1.6 Project Maturity Score and Benchmark

Maturity Score

Attributes

Total

Schedule

Cost

Requirement

Technical Understanding

Technical Difficulty

Commercial

Operations and Support

Project Stage: System Integration & Test

Benchmark

7

8

8

8

8

8

8

55

Current Project

6

7

8

9

8

7

9

54

Explanation

Schedule: Delivery of Fixed Network Final System Capability is well behind original project schedule, but is being closely managed.

Cost: Some cost risk (within bounds of contingency) remains until upgrades to in-scope Mobile platforms are finalised.

Technical Understanding: Core system has been accepted by Defence and has been supporting ADF operations since late 2004. Current stage is to deliver improvement and enhanced capabilities.

Commercial: Customer working relationship is very good but commercial/contractual issues continue to arise.

Operations and Support: Core system has been operational and supported since late 2004. Final system is currently undergoing integration and test.