Date | Amount | Factor | Explanation |
Jul 98 | 2.3 | Transfer | Transfer from other phases of JP 2043. |
Feb 99 | 0.1 | Transfer | Transfer from other phases of JP 2043. |
Feb 99 | 11 | Scope | Scope change to include Wideband High Frequency Direction Finding capability. |
May 02 | 0.9 | Transfer | Transfer for installation at Robertson. |
Feb 03 | (6.1) | Transfer | Transfer to DSG as contribution to construction of Defence Network Operations Centre and infrastructure support. |
May 03 | (1.9) | Transfer | Transfer to Facilities. |
Aug 04 | (0.2) | Budgetary Adjustment | Administrative Savings harvest. |
Aug 05 | (0.6) | Budgetary Adjustment | Skilling Australia's Defence Industry harvest. |
Total | 5.5 | Real Variation |
|