3.2 Contractor Test and Evaluation Progress
| Review | Major System/ Platform Variant | Original Planned | Current Planned | Achieved/ Forecast | Variance (Months) |
| System Integration | Final Systems (Fixed Network) | Sep 03 |
| May 08 | 56 |
| Acceptance | Core System | Mar 01 |
| Jun 04 | 39 |
| DMO Acceptance - Core System | Nov 01 |
| Oct 04 | 35 | |
| Final Systems (Fixed Network) | Feb 04 | Jul 10 | Jul 10 | 77 | |
| DMO Acceptance - Final System | May 04 | Jul 10 | Jul 10 | 74 | |
| Generic Mobiles | Dec 03 | Dec 09 | Dec 09 | 72 | |
| Variance Explanations | Core System: Contractor delays with software development and system instability. Final Systems and Mobiles: Contractor delays with software development, resource shortages and technical reviews. Note. A revised schedule was agreed with Boeing Defence Australia in the Deed of Settlement, Release and Amendment signed in April 2009. Current Planned and Forecast dates are based on this schedule. | ||||