3.3  Progress toward Initial Operational Capability

Item

Original Planned

Achieved/ Forecast

Variance (Months)

Variance Explanations/ Implications

IOC - Final System

May 04

Jul 10

74

Contractor delays with software development, resource shortages, system instability.

Deferral of operational capability.