Maturity Score | Attributes | Total | |||||||
Schedule | Cost | Requirement | Technical Understanding | Technical Difficulty | Commercial | Operations and Support | |||
Project Stage: Acceptance Into Service | Benchmark | 9 | 10 | 10 | 10 | 10 | 9 | 9 | 67 |
| Current Project | 10 | 9 | 9 | 9 | 8 | 8 | 9 | 62 |
| Explanation | Benchmark scores will be achieved as: ■ mission and support systems become fully operational; ■ operational test and evaluation is completed, principally, when davit performance is achieved, and restrictions are lifted; and ■ the contractor actually meets all requirements and there is a resolution of outstanding issues that prevent progress of FOC across the class. | |||||||